OC20-027 MDU vs KR Builders
OC20 -027 – In the Matter of the Complaint Filed by Montana Dakota Utilities Co, Rapid City, SD against KR Builders, Gillette, WY, for an incident occurring on May 12, 2020 at 811 Pine St, Whitewood, SD.
Date Filed: 06/01/2020 ♦ Deadline to Respond June 23, 2020 ♦ Pending
Documents Filed:
- 06/01/2020 - OC20-027 Complaint
- 06/03/2020 - OC20-027 - Notice of Complaint and Deadline to Respond
- 06/18/2020 - OC20-027 - South Dakota One Call Enforcement Panel Meeting Email
- 06/24/2020 - OC20-027 - Response to Complaint
- 08/04/2020 - OC20-027 Panel Recommendations and Cover letter
- 09/23/2020 - OC20-027 Signed Board Order
- 12/23/2020 - OC20-027 30 Day Demand for Payment
- 03/17/2021 - OC20 027 Summons Notification
- 04/20/2021 - OC20 027 Delivery of Summons by Cambell County Sheriff
- 08/03/2021 - OC20 027 Default Judgement
- 08/12/2021 - OC20 027 Notice of Default Judgement